Various Level Crossing

right
Various Level Crossing

At a glance

Network Rail hired us to remove and relay a level crossing in Pitsea, Essex. Using a 10-man team, we completed the job in just 28 hours, despite delays caused by restrictions placed on train movements.

  • March 2014
  • Pitsea
  • Client: Network Rail
  • Level crossing replacement
  • 10-man workforce
  • Concrete repairs and finishing
  • 28-hour around-the-clock shift
  • Excavation and re-instatement
  • Foundation replacement

services used

  • Excavation and re-instatement

  • Concrete repairs and finishing

  • Formation of roadways & footpaths

  • Foundations

completion-time

Work was completed in 28 hours

The Project In Detail

We removed crossing panels to enable Network Rail to install a new section of the track. We removed and replaced concrete bearing beams and foundations, and replaced with new. We then installed new 'strail' crossing panels and re-surfaced the approach road and applied road markings.

All of this was done working to a tight timescale set by Network Rail. This became even tighter when restrictions on train movements caused delays of approximately eight hours. Despite this, we finished the project in just 28 hours, finishing at 8am on Monday.

Accreditations

The Best Partnerships Are Built On Trust

With accreditations from Link-up, you can take the guesswork out of hiring Hall Bros. We work to the highest standards, so you can trust us to provide a full, professional service time and time again.

Contact us and find out more

Wish to discuss our services in more detail? We'd be delighted to hear from you and discuss your requirements further. Please get in touch using the details below and we will respond as soon as possible.

Please enter your name.

Please enter your email.

Your email is in the wrong format.

Please enter your telephone number.

Please enter your message.

Please confirm you are not a robot.

Contact information