Seven Kings Station

right
Seven Kings Train Station

At a glance

Hall Bros were contracted by Costain to carry out platform surface works along with the relay of copers and tactiles.

  • December 2016
  • Seven Kings Station, East London
  • Client: Costain via SEE
  • Platform surface works
  • 180m of tactiles
  • 60m of brickwork
  • Rebuild of retainer wall
  • 50 workers over three shift patterns
  • Lifting 65m and renewal of 65m of copers

services used

  • Excavation and re-instatement

  • Coping stone installation

  • Retaining walls

  • Brick & block work

  • Surfacing

  • Enabling works

completion-time

Work was completed in 9 days

The Project In Detail

This supply chain project, for Costain via SEE, started in the early hours of Christmas Day as the station was closed allowing us to avoid disruption. The works carried out required a variety of our services.

In the first seven days we successfully lifted 65m of copers, knocked down a retainer wall and our bricklaying team rebuilt it. We also started laying new copers and 180m of tactiles with temporary tarmac behind the tactiles ready for the next project. The second phase involved the installation of new white and yellow lines across the platform.

Accreditations

The Best Partnerships Are Built On Trust

With accreditations from Link-up, you can take the guesswork out of hiring Hall Bros. We work to the highest standards, so you can trust us to provide a full, professional service time and time again.

Contact us and find out more

Wish to discuss our services in more detail? We'd be delighted to hear from you and discuss your requirements further. Please get in touch using the details below and we will respond as soon as possible.

Please enter your name.

Please enter your email.

Your email is in the wrong format.

Please enter your telephone number.

Please enter your message.

Please confirm you are not a robot.

Contact information